How to Get an Injection Molding Quote (What to Send)

A custom injection molding quote arrives in 24 to 72 hours when the enquiry is complete, and takes two weeks when it is not. The difference is almost never the supplier's speed — it is whether the ten pieces of information below were in the first email.

This guide is the checklist we send to new customers, published so you can use it with any supplier.

What to send for an injection molding quote

Why quotes are slow

What the buyer sends What the supplier must do Resulting delay
"We need this part, please quote" + photo Ask for drawings, material, volume 3 – 10 days of email
STEP file only Model the tool, guess tolerances and material 2 – 5 days, and the quote is provisional
STEP + 2D drawing Price the tool and part 24 – 72 hours
Full package (this checklist) Price confidently 24 – 48 hours, and the number holds

The supplier is not being difficult. Without a drawing they cannot size the tool, without a volume they cannot amortise it, and without a material they cannot calculate the part cost. Every missing item becomes an email round trip.

The ten items to send

1. 3D model (STEP or IGES preferred)

Format Acceptable Note
STEP (.stp) Best Universal, exact geometry
IGES (.igs) Good Older but reliable
Parasolid (.x_t) Good Common from SolidWorks/NX
STL Poor Faceted, no exact surfaces — used for rough quotes only
PDF / photo Not sufficient for tooling Fine for an early indication

Ask the supplier to confirm the model opens and that draft angles are modelled in. A model without draft means the supplier must add it, which changes the part.

2. 2D drawing with tolerances

The 3D model gives geometry; the drawing gives tolerance, surface finish and critical features.

Item to include Why
General tolerance block Sets the default
Critical dimensions marked Sets where cost goes
GD&T where it matters Position, flatness, profile
Datum features Makes inspection repeatable
Surface finish callout SPI grade or Ra
Cosmetic surface definition Which faces are visible
Material and colour Named grade, not "ABS"

Our guide to tolerance specification covers how to write these so they can be inspected.

3. Material grade

"ABS" is not a material specification — it is a family. The grade decides the price:

What to state Example
Polymer and grade ABS, medium-impact, injection grade
Brand if specified LG HI-121H, or "equivalent"
Filled or unfilled 30% glass fiber
Flammability UL94 V-0 required?
Food contact FDA / EU 10/2011 required?
UV stabilised For outdoor parts
Colour Standard, custom match, or masterbatch

If you have no preference, say so — a supplier can recommend a grade and price it. What they cannot do is guess whether you need V-0.

4. Annual and monthly volume

State Why it matters
Annual quantity Sets tooling amortisation
Monthly call-off Sets cavitation and machine size
Order pattern Even, seasonal, or one-off
Expected life of the programme Sets tool life requirement

A quote for 5,000 pieces a year and one for 500,000 are different tools, different cavitation and different prices. Giving only "we need a lot" makes the quote meaningless.

5. Surface finish and appearance

Requirement What to state
Cosmetic faces Which surfaces are visible
Finish grade SPI A-1 / A-2 / B-1 / C-1 / D-1, or Ra value
Texture MT grade if textured (MT-11010, MT-11020)
Gloss Target gloss units at 60°
Colour match Standard chip, Pantone, or RAL
Acceptable defects Written limits, not "no defects"

6. Tool life and ownership

Item Options
Required shots 100k / 500k / 1M / 5M
Steel class P20, 718H, S136, H13
Ownership Buyer-owned (typical) or supplier-owned
Transfer terms Can the tool be moved later?
Maintenance Who pays, and to what schedule

Tool life is a cost driver that buyers often forget to mention. A 100,000-shot tool and a 5,000,000-shot tool for the same part can differ by 50 percent in price.

Tool life and steel selection for quoting

7. Colours and decoration

Item Detail
Colour Masterbatch, pre-compounded, or painted
Printing Pad print, screen print, laser
Assembly Clips, screws, ultrasonic welding
Inserts Metal inserts molded in or installed after
Packaging Bulk, bagged, boxed, palletised

Every secondary operation adds cost and lead time, and none of them can be priced if unstated.

8. Quality and certification requirements

Requirement Why it changes the price
ISO 9001 Baseline
IATF 16949 Automotive — PPAP, traceability
ISO 13485 Medical — validation, documentation
UL yellow card Electrical — material must be listed
First article report Inspection time
PPAP level Documentation and sampling
Material certificates Traceability

Our guide to vetting a supplier covers how to verify these claims.

9. Delivery terms and destination

Item Example
Incoterm FOB Xiamen / CIF Hamburg / EXW
Destination port or address —
Required delivery date First shipment and steady state
Shipping mode Sea, air, rail
Packaging standard Export carton spec

FOB and CIF quotes differ by the freight, and a supplier cannot quote CIF without knowing the destination.

10. Anything unusual

Item Why to flag it early
Very thin walls (under 1 mm) High injection pressure, special steel
Very thick sections (over 6 mm) Long cycle, sink risk
Undercuts Slides add tool cost
Threads Unscrewing or collapsing cores
Optical requirements Different tooling and process
Food or medical contact Material and documentation
Existing tool to be transferred Inspection and adaptation

Injection molding quote request template

Part name:
Annual volume:            Monthly call-off:
Material (grade):         Colour:
Tool life required:       Tool ownership:
Cosmetic faces:           Finish / texture:
Tolerance class:          Critical dimensions:
Secondary operations:     Assembly:
Quality standard:         Certificates needed:
Incoterm:                 Destination:
Target delivery:

Attached: STEP model, 2D drawing (PDF), reference photo (if any)

Filling this in takes 15 minutes and saves two weeks.

What a good injection molding quote contains

Line Required Why
Tooling cost, separate Yes One-off, must be visible
Cavitation and machine tonnage Yes Explains the price
Cycle time assumed Yes Checkable
Material grade and part weight Yes Checkable
Piece price at 3 volumes Yes e.g. 10k / 50k / 200k
MOQ Yes And what happens below
Lead time: tool Yes Separately from production
Lead time: production Yes —
Payment terms Yes 30/70, L/C, etc.
Packaging cost Yes Export carton is real
Tool ownership clause Yes Buyer-owned is standard
Quote validity Yes Resin prices move

A one-line quote is not a quote. Ask for the breakdown — a supplier who will not provide one either does not know their own costs or is planning to recover margin later.

Common mistakes that delay quotes

Mistake Consequence
Sending only a photo Supplier quotes a guess, then revises upward
Sending an STL Geometry approximated, quote provisional
Saying "high quality" No measurable requirement
No volume stated Tooling amortised over an assumed number
No material grade Supplier picks cheapest, part fails later
No cosmetic definition Dispute at first article
No Incoterm Price not comparable
Asking five suppliers with different info Five incompatible quotes

Timeline

Scenario Time to quote
Complete package, standard part 24 – 48 hours
Complete package, complex tool or tight tolerance 3 – 5 days
Missing 2D drawing +3 – 5 days
Missing material or volume +2 – 5 days
No 3D model 1 – 2 weeks (design must be created)

Our guides to injection molding cost explain how the numbers are built, mold cost covers the tooling side, common injection molding materials covers grade selection, supplier auditing covers due diligence, and writing an RFQ covers the documentation side.

Quote practice in this guide follows standard procurement workflow, with test and tolerance references from ASTM International and ISO, material data cross-checked against MatWeb and Engineering Toolbox, and processing practice reflecting Plastics Technology and PLASTICS industry standards, with material characterisation through SPE and NIST reference data.

What do I need to send to get an injection molding quote?

A STEP model, a 2D drawing with tolerances, the material grade, annual and monthly volume, cosmetic requirements, tool life, delivery terms and destination. With those, most suppliers quote in 24 to 48 hours.

Can I get a quote from a photo or a sample?

You can get an indication, but not a firm price. Without a 3D model the supplier must estimate geometry, and without a drawing they must assume tolerances. Expect the number to move once real data arrives.

What file format is best for quoting?

STEP (.stp) is the standard. IGES and Parasolid also work. STL is faceted geometry — acceptable for a rough indication only. PDF drawings are needed in addition to the model, not instead of it.

Why do suppliers ask so many questions?

Because each answer changes the price. Material grade, volume, tool life, tolerance and cosmetic requirements each move the tooling cost or the piece price by 10 to 50 percent. A quote without them is a guess.

How long should a quote take?

24 to 48 hours for a complete package on a standard part, three to five days for complex tools, and one to two weeks if the enquiry is missing drawings, material or volume.

What should a quote include?

Tooling as a separate line, cavitation and tonnage, cycle time, named material and part weight, price at three volumes, MOQ, lead times, payment terms, packaging and a tool ownership clause. A single number is not a quote.

Conclusion

A quote is a function of information: ten items in the first email and the price comes back in two days and holds; five items and it takes two weeks and moves twice. The template above is the whole method.

At Rui Cheng we quote from a STEP model plus a 2D drawing within 48 hours, with tooling and piece price separated, at three volumes, and with the resin grade and cycle time stated. Send the package and we will come back with a costed breakdown rather than a number.