Sampling and First Article Approval: What to Expect

Sampling is the point where a drawing becomes a part, and first article approval is where most projects either get on track or quietly go wrong — because a first article that passes is not the same thing as a process that can repeat it 200,000 times.

This guide covers the three sampling stages, what a first article report should contain, and the one check that separates a sample from a production process.

Sampling and first article approval for injection molding

The three sampling stages

Stage Who reviews What it proves Typical timing
T0 — trial shot Supplier only The tool closes, fills and ejects Days after tool completion
T1 — first article Buyer and supplier Dimensions, appearance, function 1 – 2 weeks after T0
T2 — post-correction Buyer and supplier Corrections worked, process repeatable 1 – 3 weeks after T1

Most projects need two rounds. Complex tools with slides, tight tolerance or cosmetic requirements often need three. A supplier who promises T1 approval in one round on a complex tool is either very good or not planning to be held to it.

What happens at T0

Step Detail
Mount and align Tool in the press, water and hot runner connected
Dry the resin Per the grade — this is where T0 failures usually start
Establish a process window Fill study, then packing and cooling
Shoot the first parts Usually 20 – 50 pieces
Supplier inspection Dimensions, visual, obvious defects
Report to buyer Photos, dimensions, issues found

T0 is internal. The buyer should still receive the photos and the issue list, because it sets expectations for T1.

What a first article report must contain

Item Why
Part number, revision, drawing number Confirms you are inspecting the right part
Material grade and batch/lot Traceability, and confirms the specified resin
Machine and tonnage Records what it was actually made on
Process parameters sheet Melt temp, mold temp, injection profile, packing, cooling
Dimensional results vs drawing Every dimension with nominal, tolerance, actual, pass/fail
CMM or measurement method Method matters as much as the number
Visual and cosmetic assessment Against the agreed cosmetic criteria
Photographs Overview plus detail of critical features
Assembly / function check If the part assembles or actuates
Packaging confirmation As specified or as agreed
Deviations list Anything out of spec, with a proposed fix

A first article report that is three dimensions and a photo is not a first article report.

First article inspection report

The check that separates a sample from a process

A first article is produced with the process tuned until the part passes. That is what a sample is. A production process has to hold the same result across a full shift, on a different day, with a different operator.

Ask for a capability run: 30 to 100 consecutive shots, with the critical dimensions measured every 10 shots.

What you are looking for Why
Dimension spread across the run Should be well inside tolerance, not at the edges
Where the first article sits in that spread Middle of the window = good; at one edge = the window is not centred
Cycle time consistency Drift means the process is not stable
Visual consistency Cosmetic variation across the run
Scrap count A 5 percent scrap rate in a capability run is a warning

A part that measures 25.02 mm against a 25.00 ± 0.05 mm tolerance passes. A part that measures 25.048 mm also passes — and is a much worse result, because the process has no room to drift. The capability run is what tells you which one you have.

Our guide to injection molding tolerances covers how to define the limits the run is measured against.

What the buyer should approve

Area What to check
Critical dimensions Every dimension marked as functional
Fit Assemble with the mating part, not just measure
Cosmetic Against the agreed sample or limit sample, under agreed lighting
Colour Against the approved chip, under D65 or the agreed illuminant
Function Snap fits, hinges, sealing surfaces, threads
Packaging Carton, divider, protection, labelling
Documentation FAIR, material cert, process sheet

Approval should be written, with the sample identified and dated. "Looks good" by email is not an approval — it is the beginning of a dispute three months later.

Golden sample and process lock

Item What to do
Golden sample Sign and date 3 – 5 parts, keep one at the supplier and one at the buyer
Storage Sealed, labelled, protected from light and heat
Retention period Life of the programme, plus one year
Process parameters Recorded and locked in the setup sheet
Change control Any change to resin, tool, machine or process requires re-approval

The golden sample is the reference that settles 90 percent of later arguments. Without it, "it looked better last time" cannot be resolved.

Why first articles pass and production fails

Cause Mechanism
Process at the edge of the window Passes when tuned, drifts when left alone
Different machine on the production run Same tool, different clamp and injection behaviour
Different resin lot Shrinkage varies between lots, especially in semi-crystalline grades
Operator-dependent setup Parameters copied but not verified
Tool wear during the run Dimensions drift after 50,000 shots
Moisture variation Especially PA, PBT and POM — drying discipline decays
Cosmetic criteria not written Different inspectors, different verdicts

The single biggest one is the process sitting at the edge of the window. It is why the capability run matters more than the first article itself.

Injection molding sampling timeline

Activity Duration
Tool completion to T0 1 – 3 days
T0 to T1 sample shipment 1 – 2 weeks
Buyer review of T1 3 – 10 days
Tool correction 1 – 3 weeks
T2 sample and approval 1 – 2 weeks
Production run 3 – 5 weeks after approval

A tool that needs two correction rounds adds three to five weeks to the launch. Plan for it: a schedule that assumes one round has no margin.

Sampling timeline and approval stages

Approval checklist for the buyer

Check Done
FAIR received and complete
Every critical dimension measured, not sampled
Capability run data reviewed (30 – 100 shots)
First article position within the tolerance window confirmed
Assembly with mating parts tested
Colour approved against chip
Cosmetic limit sample signed
Packaging approved
Golden samples signed and distributed
Process parameters recorded and locked
Change control clause agreed

Related guidance

Our guides to getting an injection molding quote, injection molding payment terms, vetting a supplier in China, auditing a mold supplier and injection molding MOQ cover the rest of the buying process. Defect patterns are covered in injection molding defects.

Sampling and inspection practice in this guide follows standard quality procedure, with dimensional and material test references from ASTM International and ISO, material data cross-checked against MatWeb and Engineering Toolbox, and processing guidance reflecting Plastics Technology and PLASTICS industry standards, with material characterisation through SPE and NIST reference data. For the quality-planning framework, see PPAP and first article inspection.

What is a first article inspection in injection molding?

A full dimensional, visual and functional inspection of parts from the first production tool, against the drawing, with every dimension measured rather than sampled. It should be delivered as a report with nominal, tolerance, actual and pass/fail for each characteristic.

How many sampling rounds should I expect?

Two is typical, three for complex tools. T0 is internal, T1 is the first buyer review, T2 follows tool corrections. A schedule that assumes one round has no margin for the corrections that almost always come up.

Why does my part pass first article but fail in production?

Because the first article is produced with the process tuned to pass, and production runs unattended. The gap between them is process window width — ask for a capability run of 30 to 100 consecutive shots with critical dimensions measured.

What is a capability run and why does it matter?

A run of 30 to 100 parts with the critical dimensions measured at intervals, showing the spread the process actually holds. A first article at 25.048 against 25.00 ± 0.05 passes, but leaves no room to drift.

What is a golden sample?

A signed, dated reference part, kept by both buyer and supplier, that settles cosmetic and colour disputes later. Retain it for the life of the programme plus one year, and require re-approval for any resin, tool, machine or process change.

How long does sampling take?

T0 within days of tool completion, T1 one to two weeks later, buyer review three to ten days, tool corrections one to three weeks, T2 one to two weeks. Two correction rounds adds three to five weeks to launch.

Conclusion

Sampling approval is two questions, not one: does the part meet the drawing, and can the process repeat it? The first article answers the first; the capability run answers the second. Get both, sign a golden sample, lock the process and require re-approval for changes — and the three-month argument about "it was fine at first article" never happens.

At Rui Cheng we issue a full FAIR with every sample, run a 30-shot capability check on critical dimensions as standard, and keep signed golden samples for the life of every programme. Send the drawing with the critical dimensions marked and we will quote the tool, the sampling plan and the production price. Send us your drawing →